On a yearly basis, from July 1st to June 30th, MSD reports to the State and EPA the progress and programatic measures met through NMC, CMOM, Discharge Abatement, SORP training, WQTC, SEPs and evaluating finish with performance review.
MSD-02 9/15/2025 A Dry Weather Discharge has occurred.
MSD-02 9/15/2025 A Dry Weather Discharge has occurred.
THIS REPORT CREATED AS OF: 9/15/2025 at 1:00 PM
NOTIFICATION OF POSSIBLE UNAUTHORIZED DISCHARGE DATE AND TIME DISCHARGE BEGAN: 9/15/2025 10:00 AM
ASSET ADDRESS: 911 EASTWOOD FISHERVILLE RD LOUISVILLE KY 40023 PROBLEM: FORCE MAIN BREAK INSIDE PUMP STATION VALVE ROOM COMPLETED DATE/TIME: ONGOING DISCHARGED AMOUNT: UNKNOWN, BUT GREATER THAN 1,000 GALLONS RECEIVING STREAM: FLOYDS FORK IMPACT: SEWAGE/DEBRIS FOUND ON THE GROUND MITIGATION: CONTRACTOR TO REPAIR FORCE MAIN CLEAN UP: CONTRACTOR TO CLEAN AND SANITIZE IMPACTED AREA